|
|
NASA's Space Launch System
by Ed Kyle, 01/22/2013
SLS Block 1
President Obama's February 1, 2010 cancellation of NASA's
Constellation Program left the Agency with no post-Shuttle human launch capability.
The U.S. Senate rebelled against the President, passing, on August 5, 2010, the "NASA
Authorization Act of 2010" which directed the Agency to build a new "Space
Launch System" (SLS), a big new rocket for beyond low Earth orbit (LEO)
exploration. SLS was directed to be Shuttle-Derived, using existing Shuttle or
Constellation/Ares contracts to the extent possible.
The Senate's SLS was to be developed in two phases. Phase
One would not include an upper stage, but would be able to lift 70 to 100 tons (or, by
some interpretations, metric tons or tonnes) to LEO. Phase Two would add an upper
stage, and probably other upgrades, to increase LEO payload to at least 130 tons (or
tonnes). SLS would serve as a back up for International Space Station commercial
cargo and crew, carrying humans in a new "Multi Purpose Crew Vehicle" (MPCV)
derived from the cancelled Orion spacecraft. SLS/MPCV was to be operational by
December 31, 2016.
HLLV and HEFT
NASA had begun to study alternative heavy lift launch vehicles
before Constellation was cancelled, in response to the 2009 Augustine Committee. The
"Heavy Lift Launch Vehicle" study published on May 20, 2010 compared Shuttle
Derived designs against two kerosene-fueled alternatives, one of which looked like a
modernized Saturn 5. It contemplated dropping the Ares 5 RS-68 engines for more
efficient SSME-derived RS-25 engines - a change that would allow use of a smaller
ET-derived 8.4 meter diameter tank rather than the 10 meter tank planned for Ares 5.
After the Constellation cancellation, NASA's Human Exploration
Framework Team (HEFT) reconsidered launch vehicle plans as part of its broader program
study. By September 2010, HEFT recommended a baseline heavy lift design, identified
as "5/5", that used two five-segment solid rocket boosters to lift an 8.4 meter
diameter External Tank (ET)-derived core powered by five SSME-derived RS-25E
engines. Able to lift more than 100 tonnes to LEO without an upper stage, it would
stand more than 100 meters, weigh more than 2,650 tonnes, and develop roughly 3,300 tonnes
(about 7.5 million pounds) of thrust at liftoff. This baseline SLS design was
similar to the original "classic" Ares 5 design of 2005.
HEFT
Alternatives
HEFT also contemplated, but did not recommend, an
"interim" SLS named "4/3" that would have used four-segment boosters
and a shorter core powered by only three RS-25 engines to lift 70 tonnes to LEO. Its
initial flights would actually use SSME engines pulled from retired Shuttle orbiters.
Adding an upper stage later could increase "5/5"
payloads to 130 tonnes LEO or more than 50 tonnes into deep space. HEFT left open
the question of upper stage engine type. J-2X, an "RS-25E" based
engine, or a cluster of RL-10 derived "Next Generation Engines" were
contemplated.
The Requirements Analysis Cycle
Following completion of the HEFT
study, NASA initiated the "Requirements Analysis Cycle (RAC) studies, during which
four teams of engineers analyzed alternative SLS designs. Team 1 looked at
Shuttle-Derived options. Team 2 studied
kerosene/LOX fueled alternatives. Team 3
considered modular rocket designs using existing kerosene/LOX hardware. Team 4 focused on cost reduction methods. RAC
results were provided in a March 2011 NASA briefing.
SLS RAC Team 1 Shuttle Derived
Alternatives
Team 1 presented four growth
"Blocks" in its results. "Block 0" was essentially HEFT's
"4/3", but with the standard Shuttle four segment solid rocket boosters replaced
by stacking all but the middle segment of a five-segment booster. The core was powered by three RS-25 engines, either
existing "D" engines or new "E" engines. "Block 0"
could lift 70 tonnes to LEO, could orbit astronauts in an MPCV, and aimed for a 2016
operational date.
"Block 1" would use a pair of five-segment boosters and
a longer core powered by five RS-25E engines. This operational rocket, essentially
the "5/5", would lift 100 tonnes to LEO by 2019.
An upper stage would be added to "Block 1" by 2022 to
create "Block 2". This upper stage would be powered by a single
air-start/restartable RS-25E variant. This would be the ultimate 130 tonne to LEO
SLS required to meet the Congressional requirements.
"Block 3", projected to fly in 2026, would use improved
solid rocket motors to lift up to 150 tonnes to LEO. HTPB propellant in composite
cases, replacing replace PBAN propellant in steel cases, would provide the performance
improvement.
SLS Final Choices
NASA Administrator Bolden decided to follow the HEFT
recommendations, dropping the RAC 1 "Block 0" approach. This avoided
having to develop more than one core stage and more than one solid rocket motor
design. The 8.4 meter diameter stage would be used from the outset, for 1.5 stage
Block 1, and would continue to be used for the 2.5 stage Block 2 once its upper stage was
developed. Congress forced another change when it required competition for SLS
boosters right from the start, with ATK's five segment PBAN boosters, developed for Ares
1, only used for the first few Block 1 flights. The competition would be open to
both solid and liquid booster designs. New boosters added to the Block 1 core would
create a "Block 1A" SLS.
SLS Initial and Evolved Designs
NASA formally announced its SLS plans
on September 14, 2011. "Block 1" SLS was, at the time, expected to use
"at least three" RS-25D/E core engines, but by February 2012 early design
reviews had set the number of core engines to four.
SLS Block 1
would launch MPCV spacecraft on developmental missions, using an "Interim Cryogenic
Propulsion Stage" (ICPS) for in-space propulsion. An initial "SLS-1"
(later renamed "EM-1") unmanned test flight was projected for the end of
2017. The second "SLS-2"("EM-2") launch would carry crew, but
would not occur until the end of 2021. The flights would use RS-25D engines from the
existing Space Shuttle Main Engine (SSME) inventory and existing solid rocket booster
casings.
ICPS, considered part of the SLS
payload rather than the vehicle itself, would be inserted with a 24,224 kg MPCV into a
1,800 x -93 km suborbital trajectory by SLS. The stage would then perform up to
three burns to provide more than 3,050 m/s delta-V during its mission.
The ICPS description aligned closely
with the capabilities of the existing Delta 4 Heavy upper stage. Such a stage would
be able to boost MPCV out of LEO on a circumlunar, or other deep space, mission. The
fact that Delta 4 Heavy was expected to be used for one or more MPCV boilerplate orbital
test flights made the choice logical.
By February 2012, NASA had assigned
"10000" as the "Vehicle Configuration Reference" (VCR) for SLS Block
1.
Block 1 SLS on Launch Pad. Actual SLS Vehicles will not
be Painted White.
Block 1 would only fly twice, to be
replaced by "SLS Block 1A", which would fly no earlier
than 2023. A free-for-all booster competition would lead to the development of Block
1A. Potential boosters included Advanced Composite Booster (ACB) solids using either
PBAN or HTPB propellants or kerosene/LOX Liquid Rocket Boosters (LRB) with new or existing
engines. Liquid boosters would be limited to about 5 meters diameter due to width
restrictions of the VAB doors. Either booster type would have to support the same
load path as the five segment booster, which transferred most of its force through its
upper section at the thrust beam that passed through the core intertank section.
During mid-2011, Aerojet and Teledyne
Brown announced an alliance to develop a 227 tonne thrust-class engine for the booster
competition. The "AJ-500" engine would be based, in part, on the Russian
NK-33/AJ-26 engine used by Antares. Other competitors for the booster contract
competition were likely to appear.
Block 1A would lift at least 105
tonnes to LEO. Its payloads could include ICPS or full-scale "CPS" stages.
A full-scale CPS might be able to boost Saturn 5-class payloads (about 45 tonnes)
beyond LEO. CPS was not defined, since its missions were not yet defined.
Proposed CPS designs included EELV-evolved stages powered by RL10 or RL10 follow-on
"Affordable Upper Stage Engine" (AUSE) clusters and an Ares I Upper Stage
derivative powered by a single J-2X. Proposed propellant loadings ranged from
50 to 130 tonnes, with the heavier stages burning first to reach LEO and restarting to
power payload beyond LEO.
NASA assigned the following VCR
numbers to the Block 1A concepts. Only two of these four vehicles, at most, would be
developed.
11000 Block 1 core with two ACB topped
by a cargo payload fairing
12000 Block 1 core with two LRB topped by a cargo payload fairing
13000 Block 1 core with two ACB topped by CPS/Orion/MPCV
14000 Block 1 core with two LRB topped by CPS/Orion/MPCV
SLS Block 2,
which would not fly until after 2030 at the earliest, would be a Block 1A, potentially
with a fifth RS-25E engine added to the core, topped by a new full-scale Large Upper Stage
(LUS). LUS would be powered by one to three J-2X engines, but neither engine choice
nor number of engines was fixed. Also not fixed was the basic stage construction or
its propellant loading. Concepts called for LUS, which would only be used to reach
LEO, to hold as much as 210 tonnes of propellant when three J-2X engines were used..
Block 2 would be able to lift more
than 130 tonnes to LEO or about half as much to escape velocity. It would be a
"monster rocket", weighing more than 2,900 tonnes, standing 110-120 meters, and
producing more than 4,100 tonnes of liftoff thrust.
NASA's VCR numbers for Block 2 were
21000-24000, aligned with the Block 1A numbers.
Graphic of SLS Block 1 Launch Shows RS-25 Core
Engine Pattern
NASA would budget about $18 billion to
develop and fly the SLS-1/EM-1 development mission. This would include about $10
billion to develop "Block 1", $6 billion for Orion/MPCV, and $2 billion to
create launch facilities and other infrastructure. SLS would fly from Kennedy Space
Center, where it would be stacked in the Vehicle Assembly Building on a new mobile launch
platform and launched from Launch Complex 39B. Program costs were expected to
average $3 billion per year, but that budget would probably only support one SLS/Orion
flight every two years.
NASA's SLS mission was yet to be
determined. The Agency described a potential human mission to an asteroid by 2025,
but no specific asteroid or mission plan had been selected. The Agency mentioned
that SLS could lay the groundwork for future human missions to Mars, but such missions
appeared to be decades distant at best.
Block 2 SLS was similar to Vehicle
27.3, the recommended Cargo Launch Vehicle from NASA's 2005 Exploration Architecture
Systems Study (ESAS). 27.3 was capable of lifting 146 tonnes to LEO or 60 tonnes to
a trans-lunar trajectory when it used HTPB boosters and a twin-J-2S powered upper stage
loaded with 207 tonnes of propellant. Subsequent NASA studies postulated even
heavier propellant loads.
J-2X Engine E10001 at Stennis
SLS would benefit from Ares 1 program
development efforts. During 2011, for example, the first J-2X engine, E10001, was
assembled and test fired at Stennis Space Center in Mississippi. The engine was
erected into the A-2 test stand during June. It performed an initial "burp
test" on July 14 and reached main stage during a 3.7 second test on July 26.
The engine fired for 7 seconds in early August before attempting a 50 second burn
mid-month, but the latter test had to be aborted after 32 seconds. Residual
propellants created a "back-fire" shortly after shutdown that caused some damage
to the engine. The engine was removed, repaired, and by early October returned to
the stand. It performed a 40 second test and then, by the end of November a 500
second "mission duration" test. By year's end, a second J-2X Power Pack
assembly had been installed in the A-1 test stand in preparation for more extensive
development testing using only turbopumps and engine valves.
Five
Segment Booster DM-2 Test
By the end of 2011, ATK had performed
three successful five segment booster tests at its Utah test site. The tests took
place on September 10, 2009 (DM-1), August 31, 2010 (DM-2), and September 8, 2011 (DM-3).
A precursor test of a five segment motor, assembled using an extra segment from a
Shuttle four-segment motor, occurred on October 23, 2003 (ETM-3). ATK had also
performed recovery system tests for five segment motor for Ares I, but no plans were being
made to recover the SLS boosters.
Space Launch
System Details (Subject to Change) |
| |
Oct 2005
LV 27.3 |
Oct 2005
LV 27.3 w/ EDS |
SLS Block 1
2011 Baseline |
SLS Block 1
with ICPS (2012 spec) |
SLS Block 1A (1.5 Stg)
SLS Block 2 (2.5 Stg) |
| Boosters (Each) |
5 Segment |
5 Segment |
5 Segment |
5 Segment |
New Boosters Liquid or Solid
ATK Composite Shown |
| GLOW (tonnes) |
751.084 t |
751.22 t |
729.8 t |
731.885 t |
~793 t |
| Propellant Mass (tonnes) |
650.751 t |
650.87 t |
626.10 t |
631.495 t |
~709 t |
| Burnout Mass (tonnes) |
100.333 t |
100.33 t |
103.7 t |
100.390 t |
~84 t |
| Diameter (meters) |
3.71 m |
3.71 m |
3.71 m |
3.71 m |
3.71 m |
| Height (meters) (to top of frustum) |
53.87 |
53.87 m |
53.87 m |
53.87 m |
53.87 m |
| Liftoff Thrust (vac. tonnes) |
1,578.29 t |
1,578.6 t |
1,592.47 t |
1,428.83 t |
2,041 t |
| Specific Impulse (sea level/vacuum, seconds) |
242 s/265.4 s |
237s/265.5 s |
237s/267.4 s |
237s/267.4 s |
~259/286 s |
| Burn Time (sec) |
132.5 s |
132.5 s |
126.6 s |
128.4 s |
110 s |
| Propellant |
HTPB |
HTPB |
PBAN |
PBAN |
HTPB (Example Case) |
| Core Stage |
5xSSME |
5xSSME |
4xRS25D |
4xRS25D |
4xRS25E |
| GLOW (tonnes) |
1,102.33 t |
1,092.0 t |
1,068.3 t |
1,091.4516 t |
1,091.536 t |
| Usable Propellant Mass (tonnes) |
1,004.71 t |
1,002.5 t |
978.9 t |
979.4516 t |
966.071 t |
| Burnout Mass (tonnes) |
91.155 t |
89.38 t |
89.38 t |
~112 t |
125.465 t |
| Dry Mass (tonnes) |
81.964 t |
76.12 t |
76.12 t |
~102 t |
115.577 t |
| Diameter (meters) |
8.384 m |
8.834 m |
8.834 m |
8.834 m |
8.834 m |
| Height (meters) |
64.27 m |
64.27 m |
62.54 m |
62.54 m |
62.54 m |
| Thrust (sea level/vacuum, tonnes) |
948 t/1,162 t |
948 t/1162 t |
758.4 t/929.6 t |
758.4 t/929.6 t |
758.4 t/938.04 t |
| Specific Impulse (sea level/vacuum., seconds) |
361.3 s/452.1 s |
361.3 s/452.1 s |
366 s/452.1 s |
366 s/452.1 s |
366 s/452.4 s |
| Burn Time (sec) |
411.5 s |
408.2 s |
476 s |
476 s |
476 s |
| Propellants |
LOX/LH2 |
LOX/LH2 |
LOX/LH2 |
LOX/LH2 |
LOX/LH2 |
| |
|
|
|
|
|
| Interstage |
|
|
|
4.9896 t |
5.2164 t |
| Second Stage |
|
2xJ2S |
|
Interim Cryogenic Propulsion
Stage (Delta 4 Heavy Upper Stage Assumed) |
Large Upper Stage
2xJ-2X (Boeing 2012) |
| GLOW (tonnes) |
|
229.78 t |
|
31.2075 t |
237.37 t |
| Usable Propellant Mass (tonnes) |
|
207.69 t |
|
26.8529 t |
206.02 t |
| Burnout Mass (tonnes) |
|
22.063 t |
|
4.3546 t |
30.71 t |
| Dry Mass (tonnes) |
|
19.344 t |
|
3.7649 t |
26.40 t |
| Diameter (meters) |
|
8.384 m |
|
5.1 m |
8.38 m |
| Height (meters) (including interstage) |
|
22.74 m |
|
13.7 m |
~23 m (TBD) |
| Thrust (vac., tonnes) |
|
249.02 t |
|
11.2492 t |
261.27 t |
| Specific Impulse (vac., seconds) |
|
451.5 s |
|
461.5 s |
436 s |
| Burn Time, seconds |
|
377 sec |
|
1,118 s |
344 s |
| Propellants |
|
LOX/LH2 |
|
LOX/LH2 |
LOX/LH2 |
| Payload Fairing |
40.09 x 8.38 m |
22.16 x 8.38 m |
|
|
25 x 8.38 m |
| Dry Mass (tonnes) |
10.6 t |
5.836 t |
~10.6 t |
8.1647 t |
12.11 t |
| SLS Totals |
|
|
|
|
|
| GLOW (tonnes) |
2734.27 t |
2900.30 t |
~2,650 t |
~2,650 t |
~2,700 t/2,950 t |
| Height (meters)(including payload) |
104.36 m |
109.02 m |
92.3 m |
97.56 m |
~113 m |
| Height (meters) (not including payload) |
64.27 m |
87.01 m |
64.7 m |
64.7 m |
~87 m |
| Payload (tonnes) to 48 x 296 km x 28.5 deg |
125.1 t |
146.6 t |
>70t (~95 t likely) |
|
~105 t/145 t |
| Payload (tonnes) to TLI |
|
60.6 t |
|
24.5 t |
~45 t/60 t |
References:
NASA's Exploration Systems Architecture Study
(ESAS), Final Report, NASA-TM-2005-214062, November 2005.
"Heavy Lift Launch Vehicles with Existing
Propulsion Systems", Donahue, et.al., Boeing, AIAA 2010-2310, April 2010.
Heavy Lift Launch Vehicle Study Briefing,
NASA, May 2010.
Ares Development Motor 2 Ground Test Fact
Sheet, ATK, August 2010.
Human Exploration Framework Team, Briefing,
September 2010.
Space Launch System Status, Briefing,
September, 2010.
Cryogenic Propulsion Stage, NASA, February
2011.
ATK Advanced Booster for SLS, ATK, October
2012.
The Space Launch System Capabilities for
Enabling Crewed Lunar and Mars Exploration, Boeing, October 2012.
Author
by: Ed
Kyle
Updated: 1/22/2013
Questions/Comments to
launchreport@yahoo.com
SPACE LAUNCH REPORT
by Ed Kyle
|
|